Project Dashboard

Arviat Solar Energy Project (148906)
Proposal Status: Conformity Determination Issued
Project Overview
Type of application: New
Proponent name: steve england
Company: Hamlet of Arviat
Schedule:
Start Date: 2019-05-01
End Date: 2034-10-31
Operation Type: Annual
Project Description:
The Hamlet of Arviat proposes the installation of a 250-600 kW solar photovoltaic generation project on Hamlet lands adjacent to the existing waste dump and sewage lagoons. The area covered on the Project Map captures the prospective project area. The project installation area will be less than 10% of the polygon area expressed on the Project Map. Arviat and NRStor Remotes have come together with the shared goal of implementing a comprehensive clean energy solution that significantly reduces the amount of diesel fuel required to power the community of Arviat
Personnel:
Persons: 4
Days: 60
Project Map
List of all project geometries:
ID Geometry Location Name
4213 polygon Candidate Area for Solar Project. Only a small portion of this area would be required. If there are portions within the identified polygon that are sensitive, they can be avoided.
Planning Regions:
Kitikmeot
Affected Areas and Land Types
Municipal
Settlement Area
Keewatin Planning Region
Project Land Use and Authorizations
Project Land Use
Other
Licensing Agencies
No data found.
Other Licensing Requirements
No data found.
Material Use
Equipment
Type Quantity Size Use
Vehicles 2 medium duty trucks Transport materials from Barge to Site
Cat 329 Excavator 1 Heavy Equipment Land grading at site (if required)
Cat 420E Backhoe with Auger 1 Heavy Equipment Auger holes for foundation posts. (may not be required due to project design)
Fuel Use
Type Container(s) Capacity UOM Use
Diesel 1 1 Cubic Meters Run equipment The fuel amounts required for the job are unknown,placeholder values have been added, as numerical values are required to process the request.
Hazardous Material and Chemical Use
Type Container(s) Capacity UOM Use
No records found.
Water Consumption
Daily Amount (m3) Retrieval Method Retrieval Location
0
Waste and Impacts
Environmental Impacts
Minimal impacts. - No water usage - Minimal equipment usage required for transport of solar materials, site grading, and solar foundations or anchoring installation (if necessary). - Site clean up and equipment removal following construction - Utilize power line proposed to be constructed to existing Hamlet dump and lagoon, which is adjacent to solar project
Waste Management
Waste Type Quantity Generated Treatement Method Disposal Method
No data found.
See All (0)
Categories
2018-07-19 10:40:48, from: Dan Chapman
 1. Please note that the area covered on the project map captures the prospective project area. The project installation area will be less than 10% of the polygon area expressed on the Project Map. 2. In order for the project to proceed with construction in 2019, we respectfully request NPC’s review this application as soon as is feasible. Thank you for your attention and consideration.

KEEWATIN QUESTIONAIRE

GENERAL
Environmental Protection:
s2.4.9: The applicant undertakes to prevent any new occurances of pollution, garbage and contamination at the site of the development.
YES

Removal of Fuel Drums:
s2.4.9: The applicant undertakes to remove all drums safely from the site and dispose of the drums in a safe manner.
YES

New Site Restoration and Clean Up:
s2.4.15 and Appendix 2,s1: The applicant undertakes to clean up the site and restore the site to its natural condition to the greatest extent possible.
YES

Old Site Restoration and Clean Up:
s3.13.2: The applicant undertakes to clean up the site and restore the site to its original condition to the greatest extent possible, including any work required due to the applicant's action prior to this application.
YES

Low Level Air Flights:
s5.4.4 and Apendix 2, s3: Will the applicant avoid low-level flights?
YES

Caribou Protection Measures:
s2.4.6 and Appendix 3: Will the applicant comply with the Caribou Protection Measures outlined in section 2.4.6 and in Appendix 3?
YES

Caribou Water Crossings:
Will the applicant avoid, between May 15 and September 1, to construct any camp, cache any fuel or conduct s2.4.6 and map: any blasting within 10 km of any Designated Caribou Water Crossing identified
YES

ARCHEOLOGY
Reporting of Archaeological Sites:
s4.4.3 and Appendix 3, s2 and s8: Will the applicant immediately report the discovery of all suspected archaeological sites to the Government of Nunavut?
YES

PARTICULAR AREAS
Game Sanctuary:
s2.4.1: Is the project proposal located, in whole or in part, within the Thelon Game sanctuary?
NO

Bird Sanctuary:
s2.4.1: Is the project proposal located, in whole or in part, within the Mc Connell River Migratory Bird Sanctuary, the Harry Gibbons Migratory Bird Sanctuary or, the East Bay Migratory Bird Sanctuary
NO

Southern Southampton Island and Coats Island:
s3.4.5: Is the project proposal located, in whole or in part, in southern Southampton Island and Coats Island?
NO
If yes, does the project proposal involve hydrocarbon exploration?
YES
Municipal Lands:
s1.4.3: Is the project located, in whole or in part, within municipal boundaries?
YES

PARTICULAR ACTIVITIES



New Land Use:
Does the project proposal involve a new type of land use never engaged in before in the region?
YES

Code of Good Conduct for Land Users:
Appendix 2: The applicant undertakes to adhere to the Code of Good Conduct at all times.
YES